I have searched numerous threads for Basic start data and finish, but i have not find any solution to the following issue:
I have an order type with forward scheduling and in creation i give as start i,e 10.04.16 and finish 20.04.16.
However, the operation date takes as basic start and finish the current date and not the header dates.
I have gone through thread FAQ: Maintenance Order Scheduling but no solution.
Can you please help me.