Dear All,
Chart display format should be plan start date and plan end date one bar and and Actual start date and Actual end date other bar for each order as shown in the below graph.
Data
Work Order 1 | Work Order 2 | Work Order 3 | Work Order 4 | Work Order 5 | |
Planned | 15-Jun-15 | 10-Jul-15 | 23-Jun-15 | 1-Sep-15 | 16-Oct-15 |
Planned Completion Date | 20-Jul-15 | 30-Aug-15 | 30-Sep-15 | 15-Jan-16 | 1-Feb-16 |
Actual | 17-Jun-15 | 30-Jul-15 | 23-Jun-15 | 10-Sep-15 | 20-Oct-15 |
Actual | 1-Sep-15 | In Progress | 5-Oct-15 | In Progress | In Progress |
Graph
Thanks
Regards,
Venkat